I-69 Section 5 RFP Hits the Streets

24 Oct

The Request for Proposals (RFP) for the design, construction, operations, maintenance, and financing (Design-Build-Operate-Maintain-Finance), in the official procurement jargon, just hit the streets a few days ago. Procurement documents, including all of the technical standards for construction, can be found here: I-69 Section 5.

The Final Environmental Impact Statement (FEIS) and Record of Decision (ROD) for Section 5, which provides all of the background, maps, interchange details, costs, assessed alternatives, etc., can be found here: I-69 Section 5 FEIS and ROD.

In particular, the RFP states that:

the successful Proposer (the “Developer”) shall develop, design, construct, finance, operate, and maintain the I-69 Section 5 project. The I-69 Section 5 project consists of upgrading approximately 21 miles of existing State Route 37, a four-lane median divided highway, between Bloomington, IN and Martinsville, IN to an interstate highway (the “Project”).

The Final Request for Proposals was issued 2013-10-15. Proposals are due 2014-01-21. INDOT anticipates making an award on or round 2014-02-19.

As a reminder, Section 5 goes from State Road 37 in Bloomington, IN and extends north approximately 21 miles to SR 39 in Martinsville, IN:

I-69 Section 5 Map

I-69 Section 5 Map

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: